The Contractor's Guide to Sub-Permit Sequencing

How the order in which you file trade permits determines whether your project ships on time or three weeks late.

June 10, 2026·8 min read·Editorial Team

Sub-permit sequencing is the single most under-appreciated aspect of construction scheduling. Filed in the wrong order, a full trade stack can miss inspection windows, block occupancy, and add weeks of unnecessary delay.

The dependency stack

Structural, then MEP roughs, then above-ceiling inspections, then close-in, then final trades. Each has its own permit review and its own inspection sequence. The dependency graph is a project management problem, not a paperwork problem.

The mistake we see most

GCs file the master permit and wait until construction starts before filing sub-permits. The result is trades sitting on site waiting for approvals that could have been issued three weeks earlier.

Need help on your project?

Get a written permit review for your address.

We audit scope, map the jurisdiction, and deliver a submission calendar.

Request Permit Review

Let's discuss your next project

Send us the address.
We'll take it from there.

Office

Miami · Florida
Serving Miami-Dade & Broward

Response

Same-day intake
Weekdays 8–6